News Details

Main Beach Sewer Lift Station Update

3/26/2012

The excavation and final preparation of the site took approximately 10 days longer than planned. The final concrete slabs that support the pre-manufactured lift station will be poured on Tuesday, March 27. The delivery and installation of the pre-manufactured lift station will begin on Thursday, March 29.