Construction Update:

Below is a high-level look at what has been done and what is to come in the next few weeks.

Completed to Date:

  • Asphalt Removal
  • Phase I Sidewalk removal
  • Construction of trench drains
  • Installation of storm drain and silva cell systems
  • Phase II Sidewalk removal and replacement
  • Placement of 2 specimen oak trees
  • Placement of 10 48" Box eucalyptus trees
  • Installation of A/V and electrical conduits

Upcoming Work:

  •  Installation of bollards
  • Planting and irrigation
  • Brick pavement
  • Remaining Phase II sidewalk removal and replacement
  • Installation of light poles
  • Installation of umbrella bases
Promenade Trees
Why were the trees removed?
Why did this happen so quickly / overnight?
Were the trees healthy? “They looked fine.”
What exactly was wrong with the trees?
Did the Promenade project cause this?
How many trees were affected?
Why removes instead of saved or reinforced?
Why not remove fewer trees?
What will replace the removed trees?
How will the new trees be different?
How long will it take for the trees to grow back?
Why plant eucalyptus again?
Will the remaining trees be safe?

History and Background

Timeline

Approved Design by Planning Commission

The Planning Commission’s approved design is here, and the approved resolution is here.

Promenade on Forest Key Features:

• Removal of existing curb and gutter
• Addition of linear trench drains
• Addition of permeable surfaces and brick pavers 
• Landscaped gardens consisting of shrubs, vining plants, and groundcover, to include flowering plants for added color
• Areas for seating and dining
• Designated areas for temporary performances
• Wider storefront walkways
• New tree plantings
• Drainage system

Project Meetings

The City has held public meetings, workshops, and focus groups discussions with City staff, the City Council ad hoc committee, and/or certain City legislative bodies, that have collaborated with property owners, business owners, and residents in regards to the project, including but not limited to the following efforts:

  • The City conducted public workshops on September 22, 2022, and May 17, 2023.
  • The City Council held public meetings on January 12, 2021, May 18, 2021, June 7, 2022, January 23, 2024, February 27, 2024, April 23, 2024, February 4, 2025, and April 8, 2025 discussing, over the course of those meetings, a permanent Promenade Project with the closure of Lower Forest to vehicular traffic and various design iterations.
  • The Planning Commission held public meetings on July 5, 2023, February 4, 2025, February 26, 2025 and April 2, 2025 to review various design iterations.
  • The City Council Ad Hoc Committee for the Promenade on Forest Project met with property and business owners in the project area for focus groups (Architects/Planners, Community, Restaurant, and Retail Groups). On April 17, 2024, May 7, 2024, September 19, 2024, and January 7, 2025, the Ad Hoc Committee conducted several meetings on each date with the respective the focus groups, who were provided updates on the Project and opportunity to provide feedback. 
  • The City Council Ad Hoc Committee also informally discussed on multiple occasions with property and business owners in the Project area the proposed Project and the street closure.